PART 1: SAN JUAN COUNTY WATERSHED MANAGEMENT ACTION PLAN


CHAPTER 3: ACTION STRATEGIES, COUNTY-WIDE


County-Wide Action Strategies

Introduction:

The goals of the Watershed Advisory Committee are to develop durable solutions to prevent, reduce, and eliminate non-point sources of pollution that can negatively impact the beneficial uses of surface waters, both fresh and marine, and ground water county-wide. These durable solutions have been coined "Action Strategies" and are listed below.

The Action Strategies were developed to address the pollution problem statements contained in the preceding chapter. These strategies were developed after months of technical presentations, discussions with implementing agencies, committee discussions, and public workshops. The strategies identify implementing agencies as well as additional participating entities. The strategies were assigned an implementation schedule consisting of a start and completion date. Implementation costs were projected based on the following three categories:

 Low:  Implementation with existing staff with total cost not to exceed $10,000
 Moderate:  Implementation with existing staff or under contract, cost between $10,000 and $50,000
 High:  Additional staff needed, cost in excess of $50,000

See Section 4, Implementation Strategies, for more detailed estimates of implementation costs.

The strategies contain recommendations for new regulations, proposed regulation changes, development and implementation of Best Management Practices (BMPs), financial incentives, education, monitoring, and inventories. The Action Strategies are listed below, starting with overall water quality strategies and then by source of pollution.

Water Quality Strategies:

 WQ1: Develop and fund a long term water quality monitoring program to measure the cumulative impacts of non-point source pollution including but not limited to; sewage disposal, land conversions, stormwater, agricultural, forestry, marinas and recreational boating, and solid and hazardous waste.

Implementing Agency:

San Juan County Health & Community Services

Participating Agencies:

Board of County Commissioners

Cost:

High

Implementation Schedule:

Immediate on adoption of monitoring plan, On-going

 WQ2:  Inform Realtors, Developers, Regulators, Decisions Makers, Contractors, Planners, and Property Owners about wetlands and non-point sources of pollution including, but not limited to, septic systems, land conversions, stormwater, agricultural and forestry practices, marinas and boating, and solid waste.

Implementing Agency:

San Juan County Permit Center, Health and Community Services, Planning Department, Public Works, and Conservation District

Participating Agencies:

Department of Ecology, Department of Health,

Cost:

Moderate

Implementation Schedule:

Year 1, On-going

WQ3:   Update the United States Department of Agriculture Soil Survey for San Juan County.

Implementing Agency:

San Juan County Board of Commissioners

Participating Agencies:

San Juan County Conservation District, San Juan Planning Department, & Natural Resource Conservation Service

Cost:

High

Implementation Schedule:

Year 1 to 5

 WQ4: Review and revise, if appropriate, wetlands regulations, Section 3.6.8 of the Unified Development Code for consistency with good water quality management and best management practices.

Implementing Agency:

San Juan County Planning Department

Participating Agencies:

 

Cost:

Moderate

Implementation Schedule:

Year 2

 WQ5: Update and maintain the county's wetland inventory in a computerized GIS format with information developed from jurisdictional wetland delineations.

Implementing Agency:

San Juan County Permit Center

Participating Agencies:

 

Cost:

Moderate

Implementation Schedule:

Year 1, Ongoing

 WQ6: Train county personnel and interested parties in wetland identification.

Implementing Agency:

San Juan County Health and Community Services, Permit Center, and Conservation District

Participating Agencies:

Department of Ecology

Cost:

Low

Implementation Schedule:

Year 1, On-going

 WQ7: Coordinate with and utilize public schools and other private and public organizations in long term water quality monitoring efforts.

Implementing Agency:

San Juan County Conservation District, WSU Extension Service

Participating Agencies:

Public Schools & Non-Profit Groups

Cost:

Low

Implementation Schedule:

Year 1, On-going

 WQ8: Utilize an early warning threshold of no more than 10% of the samples used to calculate the geometric mean exceed 10 cfu/100mL in marine waters for San Juan County shellfish water quality monitoring. This early warning should initiate an investigation of sources of contamination, such as sanitary surveys for failing septic systems and inventories of upland farm practices.

Implementing Agency:

SJC Health and Community Services

Participating Agencies:

SJC Conservation District, Washington State Department of Health Shellfish Program

Cost:

Low

Implementation Schedule:

Immediate

 WQ9: Complete a computerized geographic information system (GIS) of watershed characteristics for all of San Juan County and continue to develop resource information to complete a watershed management database for resource technicians and planners, permit staff, developers, conservation groups, and citizens of the county.

Implementing Agency:

San Juan County GIS

Participating Agencies:

San Juan County Health and Community Services, Planning, Permit Center, Conservation District, Washington State Department of Natural Resources, Department of Fish and Wildlife, Department of Ecology, the US Geologic Survey, and universities

Cost:

Moderate

Implementation Schedule:

Immediate

Implementing Agency:

San Juan County Land Bank, San Juan County Planning

Participating Agencies:

San Juan County Health and Community Services, San Juan County Conservation District

Cost:

Moderate

Implementation Schedule:

Year 1

Implementing Agency:

San Juan County Planning

Participating Agencies:

 

Cost:

High

Implementation Schedule:

3

Implementing Agency:

San Juan County Health and Community Services

Participating Agencies:

Planning

Cost:

Moderate

Implementation Schedule:

Year 3, On-going

 

On-site Sewage System Strategies:

 OS1: Inform homeowners, Realtors, and contractors about proper septic system operation and maintenance. Information sources should include, articles in newspaper similar to "OPALCO Gram", brochures, column in Realtor newsletters, yearly workshops, and "owner manuals."

Implementing Agency:

San Juan County Health and Community Services

Participating Agencies:

Conservation District

Cost:

Moderate

Implementation Schedule:

Year 1, On-going

 OS2: Continue to inform property owners that low interest loan money is available to repair failed septic systems.

Implementing Agency:

San Juan County Health and Community Services

Participating Agencies:

 

Cost:

Low

Implementation Schedule:

Ongoing

 OS3: Facilitate workshops with septic tank pumpers and maintenance providers about contracting with homeowners' groups, including non-ferry islands, for services at a reduced cost.

Implementing Agency:

San Juan County Health and Community Services

Participating Agencies:

 

Cost:

Moderate

Implementation Schedule:

Year 2

Implementing Agency:

San Juan County Health and Community Services

Participating Agencies:

San Juan County Permit Center, San Juan County Auditor

Cost:

Moderate to High

Implementation Schedule:

Year 1, On-going

Implementing Agency:

San Juan County Health and Community Services

Participating Agencies:

 

Cost:

Low

Implementation Schedule:

Year 1, On-going

Implementing Agency:

San Juan County Health & Community Services

Cost:

Low

Implementation Schedule:

Year 1, On-going

Implementing Agency:

San Juan County Health and Community Services

Participating Agencies:

 

Cost:

Low

Implementation Schedule:

Year 1, On-going

Implementing Agency:

San Juan County Health & Community Services

Participating Agencies:

 

Cost:

Moderate

Implementation Schedule:

Year 1, On-going

 OS9:  Develop and implement a comprehensive septage and sludge management plan for San Juan County.

Implementing Agency:

San Juan County Public Works

Participating Agencies:

San Juan County Board of Commissioners, San Juan County Health & Community Services

Cost:

High

Implementation Schedule:

Year 3

 OS10: Construct a septage treatment facility on San Juan Island to reduce septic tank pumping cost.

Implementing Agency:

San Juan County Public Works

Participating Agencies:

San Juan County Board of Commissioners, San Juan County Health & Community Services

Cost:

High

Implementation Schedule:

Year 1

 OS11: Provide adequate funding to maintain an effective operation and maintenance (O&M) program. The county needs to provide and maintain the necessary funding and resources to sustain an effective O&M program.

Implementing Agency:

San Juan County Board of Commissioners

Participating Agencies:

San Juan County Health and Community Services

Cost:

High

Implementation Schedule:

Year 1, On-going

 OS12: Continue to pursue funding for sanitary surveys in areas of the county with high risk for septic failure, such as: areas where water quality monitoring shows elevated levels of fecal contamination and areas where older subdivisions and septic systems have a direct impact on the shoreline or drainage.

Implementing Agency:

San Juan County Health and Community Services

Participating Agencies:

San Juan County Conservation District, Washington State Department of Ecology

Cost:

Moderate

Implementation Schedule:

On-going

 OS13: San Juan County should continue to encourage alternative and experimental on-site systems and monitor on performance-based criteria.

Implementing Agency:

San Juan County Health and Community Services

Participating Agencies:

Washington State Department of Ecology

Cost:

Moderate

Implementation Schedule:

On-going

 

Land Conversion Strategies:

 LC1: Review and revise, if appropriate, Clearing and Grading regulations, Section 6.6.5A of the Unified Development Code for consistency with good water quality management and best management practices.

Implementing Agency:

San Juan County Planning Department

Participating Agencies:

 

Cost:

Moderate

Implementation Schedule:

Year 2

 LC2: Insure implementation of BMPs for clearing and grading are instituted for all land development, including single family residences.

Implementing Agency:

San Juan County Permit Center

Participating Agencies:

SJC Public Works, Department of Ecology

Cost:

Moderate

Implementation Schedule:

Year 3, On-going

 LC3:  Develop and insure implementation of Small Parcel Drainage plans for land development, including single family residences.

Implementing Agency:

San Juan County Permit Center

Participating Agencies:

Public Works, Department of Ecology

Cost:

Moderate

Implementation Schedule:

Year 3, On-going

 LC4:  Provide incentives to property owners to decrease densities on undeveloped property.

Implementing Agency:

San Juan County Planning Department

Participating Agencies:

Board of County Commissioners, Land Bank

Cost:

Moderate to High

Implementation Schedule:

Year 3

 LC5:  Inform developers, Realtors, and property owners on all issues surrounding land conversions (i.e.; "ConversionGram" and newsletters)

Implementing Agency:

San Juan County Permit Center

Participating Agencies:

Department of Ecology

Cost:

Moderate

Implementation Schedule:

Year 1, On-going

 LC6: Develop resource management overviews for county staff, developers, property owners and homebuyers using existing data and technology.

Implementing Agency:

San Juan County Conservation District

Participating Agencies:

San Juan County Planning, Permit Center, Environmental Health and GIS

Cost:

Moderate

Implementation Schedule:

Year 2, On-going

 LC7: Develop and implement policies and procedures for assessing the cumulative impacts of land conversion and development on a watershed basis. This should include identifying baseline conditions, thresholds of unacceptable change, and remediation/regulation to address unacceptable impacts if determined to be necessary.

Implementing Agency:

San Juan County Planning Department

Participating Agencies:

 

Cost:

Moderate

Implementation Schedule:

Year 2, On-going

 LC8: For all subdivisions, require conservation design plans to protect critical habitat, resource lands, aquifer recharge, and surface water supplies.

Implementing Agency:

San Juan County Planning Department

Participating Agencies:

Permit Center

Cost:

Moderate

Implementation Schedule:

Year 2, On-going

 

Stormwater Runoff Strategies:

 SW1:  Improve enforcement of stormwater control measures, through inspection, to insure their effectiveness.

Implementing Agency:

San Juan County Permit Center

Participating Agencies:

San Juan County Public Works, Town of Friday Harbor

Cost:

Moderate

Implementation Schedule:

Year 3, On-going

 SW2: Require contractors that construct stormwater facilities be certified by the Department of Transportation or other reputable organization (such as, IECA) in surface water run-off, erosion, and sediment control.

Implementing Agency:

San Juan County Permit Center

Participating Agencies:

San Juan County Public Works, Town of Friday Harbor

Cost:

Low

Implementation Schedule:

Year 2, On-going

 SW3:  Require an "as-built" drawing and operation and maintenance manual be completed and submitted on all new and revised permanent stormwater facilities.

Implementing Agency:

San Juan County Permit Center

Participating Agencies:

San Juan County Public Works, Town of Friday Harbor

Cost:

Low

Implementation Schedule:

Year 1, On-going

 SW4:  Develop a Best Management Practice (BMPs) manual for stormwater that is specific to rural development in San Juan County.

Implementing Agency:

San Juan County Planning Department

Participating Agencies:

SJC Public Works

Cost:

Moderate

Implementation Schedule:

Year 2

 SW5: Inform developers, contractors, and property owners of the methods and benefits of BMP implementation for stormwater, erosion, and sediment control (e.g.; "ConversionGram" etc.)

Implementing Agency:

San Juan County Planning Department

Participating Agencies:

 

Cost:

Moderate

Implementation Schedule:

Year 2, On-going

 

Agriculture Practices Strategies:

 AP1:  Inform property owners and farmers of the existence of Best Management Practices (BMPs) and their benefits for all conventional and exotic livestock. The Conservation District (CD) should actively contact farmers to explain BMPs, the benefits received, and investigate the obstacles to BMP implementation.

Implementing Agency:

San Juan County Conservation District

Participating Agencies:

 

Cost:

Low

Implementation Schedule:

On-going

 AP2: Conduct an inventory to identify farmland and numbers of animals countywide. An accurate survey is needed to assess the total extent of farming activities including potential water quality problems.

Implementing Agency:

San Juan County Conservation District

Participating Agencies:

Natural Resource Conservation Service

Cost:

Moderate

Implementation Schedule:

Year 1

 AP3: Review and revise, if appropriate, Section 4.2, Agricultural Activities, Best Management Practices for Water Quality, in the Unified Development Code.

Implementing Agency:

SJC Planning Department

Participating Agencies:

San Juan County Conservation District

Cost:

Moderate

Implementation Schedule:

Year 2, On-going

 AP4: Develop and activate a Memorandum of Understanding (MOU) between the Department of Ecology and San Juan County to clarify the various agencies roles and responsibility in preventing water quality degradation from farming activities.

Implementing Agency:

Department of Ecology

Participating Agencies:

San Juan County Conservation District, Permit Center

Cost:

Low

Implementation Schedule:

Year 2, On-going

 AP5:  Identify and obtain cost share funds to assist farmers in implementing BMPs.

Implementing Agency:

San Juan County Conservation District

Participating Agencies:

 

Cost:

Moderate

Implementation Schedule:

On-going

 

Forest Practices Strategies:

 FP1:  Inform landowners and loggers of the requirements of the forest practice rules and benefits of BMPs.

Implementing Agency:

Department of Natural Resources

Participating Agencies:

San Juan County Conservation District, Permit Center

Cost:

Moderate

Implementation Schedule:

Year 1, On-going

 FP2: Develop and implement a program to present information to landowners, loggers, and contractors who clear and grade property through workshops and training on BMPs and site specific conditions in San Juan County, including identification of wetlands, important habitat characteristics, and the importance of preventing erosion and sedimentation. Ongoing education should be a part of this program.

Implementing Agency:

San Juan County Conservation District

Participating Agencies:

Department of Natural Resources, Permit Center

Cost:

Moderate

Implementation Schedule:

Year 1, On-going

 FP3:  Develop Best Management Practices (BMPs) specific to San Juan County that relate to clearing and grading, roads, skid trails, and revegetation that promote watershed stabilization and reduction of surface water run-off, erosion, and off-site sediment impacts.

 FP4:  Develop and require implementation of BMPs or guidelines to protect habitat and water quality as well as timber management for land classified as Timber Open Space and Designated Forest Land.

Implementing Agency:

Department of Natural Resources & San Juan County Planning Department

Participating Agencies:

San Juan County Assessor

Cost:

Moderate

Implementation Schedule:

Year 2, On-going

 FP5: The Department of Natural Resources (DNR) needs to monitor and provide the necessary enforcement to insure BMPs are implemented for all timber harvest activities to promote watershed stabilization and reduction of surface water run-off, erosion, and off-site sediment impacts. Explore possibility of utilizing a volunteer citizen group to monitor and report to DNR.

Implementing Agency:

Department of Natural Resources

Participating Agencies:

 

Cost:

Moderate

Implementation Schedule:

Year 2, On-going

 FP6:  Review and revise, if appropriate, the Forest Practices regulations, Section 3.6.8D(1) of the Unified Development Code for consistency with good water quality management and best management practices.

Implementing Agency:

SJC Planning Department

Participating Agencies:

 

Cost:

Moderate

Implementation Schedule:

Year 2, On-going

 FP7: Develop a memorandum of understanding with Department of Natural Resources to provide specific, current county information for their review of forest practice permits.

Implementing Agency:

San Juan County Planning Department

Participating Agencies:

San Juan County Permit Center, Department of Natural Resources

Cost:

Moderate

Implementation Schedule:

Year 1, On-going

 FP8: Develop and utilize a computer tracking system, which includes mapping of activities, for forest practice applications and subsequent land development.

Implementing Agency:

San Juan County Permit Center

Participating Agencies:

 

Cost:

Moderate

Implementation Schedule:

Year 2, On-going

Marinas and Recreational Boating Strategies:

MR1:  Facilitate a survey at marinas and recreational areas and high traffic areas to determine the number of boats, overnight activity, number of mooring buoys, use of pump-out facilities and discharge areas in San Juan County.

Implementing Agency:

Planning Department/Marine Resource Committee

Participating Agencies:

Port of Friday Harbor, State Parks and Recreation

Cost:

Moderate

Implementation Schedule:

Year 1

 MR2:  Disseminate educational material to boaters on the effects of illegal discharges, particularly on shallow poor flushing bays and other sensitive areas.

Implementing Agency:

Planning Department/Marine Resource Committee

Participating Agencies:

Port of Friday Harbor, State Parks and Recreation, Stewardship Network

Cost:

Low

Implementation Schedule:

Year 2, On-going

 MR3:  Pursue obtaining funding to develop additional pump-out facilities, either portable or at marinas, and their continue operation, making it easier for boaters to dispose of their waste. In addition, final waste disposal areas will need to be identified.

Implementing Agency:

WS Parks and Recreation

Participating Agencies:

Port of Friday Harbor, State Parks and Recreation, National Parks Service, & San Juan County Health and Community Services

Cost:

High

Implementation Schedule:

Year 1 to Year 3

 

Solid and Hazardous Waste Strategies:

 SH1:  Inventory and evaluate all unregulated landfills.

Implementing Agency:

San Juan County Health & Community Services

Participating Agencies:

Department of Ecology

Cost:

Moderate

Implementation Schedule:

Year 2,

 SH2: Continue to subsidize cost for proper disposal and recycling of household hazardous waste. Additional funds should be sought to increase existing services.

Implementing Agency:

San Juan County Public Works

Participating Agencies:

Town of Friday Harbor

Cost:

Low

Implementation Schedule:

Year 1, On-going

 SH3:  Continue to and increase the dissemination of information on what constitutes hazardous waste and how to limit or eliminate their use. Focus should be given to agricultural operations as well as to individual households

Implementing Agency:

San Juan County Public Works

Participating Agencies:

San Juan County Conservation District, Town of Friday Harbor

Cost:

Low

Implementation Schedule:

Year 1, On-going

 SH4:  Continue to support and increase county's efforts to recycle.

Implementing Agency:

San Juan County Public Works

Participating Agencies:

San Juan County Conservation District, Town of Friday Harbor

Cost:

Low

Implementation Schedule:

On-going

 SH5: Develop and enforce regulation on illegal dumping and other solid waste violations.

Implementing Agency:

San Juan County Health and Community Services

Participating Agencies:

Cost:

Moderate

Implementation Schedule:

Year 2, On-going

 

 SH6: Develop an education program for contractors to encourage recycling and proper disposal of waste materials and require that building and demolition contractors fill out a waste management plan before projects are begun.

Implementing Agency:

San Juan County Permit Center, Town of Friday Harbor

Participating Agencies:

San Juan County Public Works

Cost:

Moderate

Implementation Schedule:

Year 2, On-going

 